Wednesday, 10 August 2022

Min-Max Planning

 

MIN-MAX PLANNING

                             Source type = SUPPLIER

·         First create the item

·       In General Tab do the following

 


Now we need to run Planning program

Go to ->Inv -> Planning ->  Min-Max Planning



After Program Completion

Go to -> Purchasing Responsibility

And run a Program Requisition Import



If the program is completed then these three program have to be completed



 

Now let’s go and check whether the Requisition is created or not

          


Requisition got created and Approved Also.

Now we can convert it into the PO.

No comments:

Post a Comment

Inventory - Physical Counting

  PHYSICAL COUNTING It is  used to verify the On-hand System Quantity and Actual Quantity of the item based on Sub inventory or Organization...