MIN-MAX PLANNING
Source type = SUPPLIER
·
First create the item
·
In General Tab do the following
Now we need to run Planning program
Go to ->Inv -> Planning -> Min-Max Planning
After Program Completion
Go to -> Purchasing Responsibility
And run a Program Requisition Import
If the program is completed then these
three program have to be completed
Now let’s go and check whether the
Requisition is created or not
Requisition got created and Approved Also.
Now we can convert it into the PO.